H-2A TIMELINE

Desired Worker Start Date
Desired Worker End Date

*The following timeline serves as an informative guide, specific dates may vary on a case by case basis

  • Sat Dec 28 2024
    90 Days
    Earliest date to submit worker orders (names and/or returning worker hires) for facilitator action, if using a MAS preferred provider
  • Sun Jan 12 2025
    75 Days
    Earliest date Job Order (ETA 790A) may be submitted to the State Workforce Agency (SWA)
  • Sun Jan 19 2025
    68 Days
    Anticipated SWA acceptance date and submission date for H-2A Application (ETA 9142) to the U.S. Department of Labor (DOL)
  • Sun Jan 26 2025
    61 Days
    Anticipated DOL acceptance date and start of recruitment period
  • Mon Jan 27 2025
    60 Days
    Latest date Job Order (ETA 790A) may be submitted to the SWA for non-emergency filings
  • Tue Feb 11 2025
    45 Days
    Latest submission date for H-2A Application (ETA 9142) to DOL and latest date to submit an emergency filing
  • Mon Feb 24 2025
    32 Days
    Due date for Recruitment Report submission to DOL
  • Wed Feb 26 2025
    30 Days
    Anticipated approval date for H-2A Labor Certification
  • Thu Feb 27 2025
    29 Days
    Anticipated receipt date for Visa Petition (I-129) filing with U.S. Citizenship and Immigration Services (USCIS)
  • Thu Mar 13 2025
    15 Days
    Anticipated approval date for I-129 visa petition and earliest date for consular appointment scheduling
  • Sat Mar 22 2025
    6 Days
    Anticipated consular appointment date for foreign H-2A workers
  • Wed Mar 26 2025
    2 Days
    Anticipated worker arrival
  • Fri Mar 28 2025
    Start Date
    Contract start date